12 workers can do a peice of work in 20 days. How many workers should be added to complete work in 16 days?​

Respuesta :

atchleyamirah69
atchleyamirah69 atchleyamirah69
  • 01-04-2021
3 workers

if 12 workers can do a piece of work in 20 days, then one person can do it in 240 days. 240/16 is 15. That is the number of workers that you need in total to it in 16 days. Since the question ask how many more workers,
15 - 12 = 3 more workers.
Answer Link

Otras preguntas

Why did Phoenicians developed a currency?HELP ASAP
find the pair of numberswhose sum is 40 and whose product is a maximum.
explain how there can be more heat energy in an iceberg than in a pot of boiling water
did benjamin franklin have access to invisible ink?
_____ is support that relies on the credibility of the author. a. ethos b. pathos c. none of the choices d. manipulation
All animals are a. land-dwelling multicellular heterotrophs. b. capable of walking on legs. c. multicellular, heterotrophic and lack cell walls. d. unicellu
If a society answers the three basic economic questions by relying on ritual, ancestral laws, and religious dictates, what type of economic system is it using?
Give me facts on ants (10 facts)
A homogeneous mixture is a mixture in which the composition is not uniform throughout. a. true b. false
What is the best way to describe paraphrasing?