Is typically not referred to as a buffer type in critical chain project management?

Respuesta :

dinosaurbarn
dinosaurbarn dinosaurbarn
  • 14-01-2018

The answer is Free Buffer. Project buffer, a not usual and the only one buffer to protect the project deadline;

Feeding buffer it is different types of buffers to protect parts of the critical chain. And resource buffer is a multiple artificial buffers that act as warning signals to assure that it is available of resources.

Answer Link

Otras preguntas

In what way does George’s climate most impact its economic development
Billy and Michael have 2 lemonade stands. Billy charges $2 per lemonade plus a flat rate of $2. Michael charges $3 per lemonade plus a flat rate of $1. How many
What are the slope and y-intercept on the graph of the linear equation on the grid?​
What overall insight or theme is revealed in the monkey's paw.
Both A and R are true, R is the correct explanation for A Both A and R are true, R is not the correct explanation for A A is true, R is false A is false, R is t
What is the slope of the given slide?
What is the function of tendons?
why can Aalam Channa not wear off the rack clothes​
Can anyone help with these questions?
Which of the following selections best summarizes the speaker’s theory? A. Taking photographs is a good way to remember the past. B. In order to learn about the